There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to:

Answers

Answer 1

Answer:

the standard deviation of the critical path is 8

Step-by-step explanation:

The computation of the standard deviation of the critical path is shown below:

As we know that

Variance = Standard deviation^2

Now the variance of the critical path is

= Variance 1 + variance 2 + variance 3 + variance 4

= 4^2 + 4^2 + 4^2 + 4^2

= 64

Now the standard deviation would be

= √64

= 8

hence, the standard deviation of the critical path is 8


Related Questions

Evaluate. 1 1/2÷4
A. 2 1/2
B. 12/2
C. 3/8
D. 6

Answers

the correct answer is C. 3/8

the correct answer is C. 3/8

Two people are pulling on a rope in order to get a 2250-kg car out of a mud puddle. One person pulls with a force of 600 N and the other pulls with a force of 800 N. There is a resistive frictional force of 1200 N. What will the acceleration of the car be? (answer with 3 digits, units will be m/s/s, DO NOT put them. ) *

Answers

Assuming both people are pulling in the same direction, the net force on the car is, according to Newton's second law,

600 N + 800 N - 1200 N = (2250 kg) a

Solve for the acceleration a :

200 N = (2250 kg) a

a = (200 N) / (2250 kg)

a0.0889 m/s/s

sgshnsjmsngtjsdyjhsksykhm​

Answers

i can't read it, its too blurry

anyways have a great day/night :)

a tortoise is walking in a desert. it walks at a speed of 5 meters per minute for 156.25 meters. for how many minutes does it walk?​

Answers

Answer:

31 1/4 minutes

Step-by-step explanation:

156.25/5= 31.25

Answer:

31.25 minutes

Step-by-step explanation:

156.25 divided by 5 is 31.25

Nick bought 5 tickets to go to the amusement park for $65. If he wanted to buy 8 tickets, what would that cost him?

Answers

Answer:

$104

Step-by-step explanation:

First find how much 1 ticket costs

65/5= 13

Times that by 8

8x13=104

(PLEASE HELP THIS IS TIMED!!!)

Which graph represents the inequality x > 6?

Answers

Answer:

The last one

Step-by-step explanation

x is greater than six so you would go to the right and it has to be an open dot since it can't be the same as 6

Answer:

hello

Step-by-step explanation:

fraction or decimals that stop are known as _____numbers.
Partial
Rational

Answers

The answer is rational

Answer:

Step-by-step explanation:

Rational numbers are numbers that are terminating decimals or nonterminating, repeating decimals.

Like 3, -4, 7.166..

In each triangle ABC, angle C is a right angle. Find the value of the trig function indicated.

Answers

As given triangle ABC, angle C is a right angle if a=6, c=10 then value of trigonometric function is  sin A = 3/5.

As given in the question,

In triangle ABC,

∠C  = 90°

Side a is opposite to angle A

c is the hypotenuse opposite to angle C

a = 6

c = 10

sin A = ( opposite side) / Hypotenuse

⇒sin A = a/c

⇒sin A = 6/10

⇒sin A = 3/5

Therefore, as given triangle ABC, angle C is a right angle if a=6, c=10 then value of trigonometric function is sin A = 3/5.

Learn more about trigonometric function here

brainly.com/question/14746686

#SPJ1

What are the roots of f(x)=x^3-x^2-5x-3?

Answers

Answer:

x=3 and x=-1

Step-by-step explanation:

Given Descartes' Rule of Signs, there is only one positive root and one negative root.

The Rational Root Theorem states that if a polynomial zeroes for a rational number P/Q then P is a factor of the Trailing Constant and Q is a factor of the Leading Coefficient.

So P could be +1, -1, +3, or -3, while Q could be 1 or -1.

Therefore, P/Q could be +1, -1, +3, or -3.

Then we use synthetic division to find the correct factor(s):

1 | 1 -1 -5   -3

___ 1_0_ -5

   1  0 -5 | -8

So (x-1) is not a factor

-1 | 1 -1 -5   -3

___-1_2_  3

    1 -2 -3 |  0

So (x+1) is a factor where the quotient is x^2-2x-3 or (x-3)(x+1)

3 | 1 -1 -5   -3

___ 3_6_ 3

    1  2  1 |  0

So (x-3) is a factor where the quotient is x^2+2x+1 or (x+1)^2

Given (x-3) and (x+1) are factors, we now use the Zero Product Property:

(x-3)(x+1)=0

x-3=0

x=3

x+1=0

x=-1

So the roots are x=3 and x=-1

Which shape is similar to shape x?

Answers

Answer:

the c one

Step-by-step explanation:

hope it will help

Answer:

Step-by-step explanation:

Probably C but I sure wouldn't bet the farm on it. It looks like C is about 1.5 times the size of X

Please I need some answers

Answers

The answer to this question is -5

Please I need help with the question

Answers

Answer: Yes please tell us the question.

Step-by-step explanation:

Can you attach a photo of the question please? thx!

A ball is thrown from an initial height of 4 feet with an initial upward velocity of 30ft/s. The balls height h (in feet) after t seconds is given by the following. H=4+30t-16t^2n

Answers

The maximum height of the ball is at 18.0625 feet which occurs at 0.9375 s

What is an equation?

An equation is an expression that shows the relationship between two or more variables and numbers.

Let h represent the height of the ball after t seconds, hence:

h(t) = 4 + 30t - 16t²

The maximum height is at h'(t) = 0, hence:

h'(t) = 30 - 32t

-32t + 30 = 0

t = 0.9375 s

h(0.9375) = 4 + 30(0.9375) - 16(0.9375)² = 18.0625 feet

The maximum height of the ball is at 18.0625 feet which occurs at 0.9375 s

Find out more on equation at: https://brainly.com/question/13763238

#SPJ1

The function W(t) = 40e^–0.35t models the healing of a wound after t hours, where W(t) represents the wound area in square millimeters. What relationship do W(t) and t have?
when t = 0, W(t) > 40
when t = 0, W(t) 0, W(t) > 40
when t > 0, W(t) < 40

ASAP I'm taking test

Answers

Answer:

Pretty sure its D.

Step-by-step explanation:

Whenever I made t something higher than 0 I got something less than 40|

(Sorry if I didn't make it in time and if I did I'm taking the same test rn gl homie)

The value of function W(t) will be less then 40 if t > 0 thus option (D) is correct.

What is a function?

A certain kind of relationship called a function binds inputs to essentially one output.

In other words, the function is a relationship between variables, and the nature of the relationship defines the function for example y = sinx and y = x +6 like that.

As per the given function,

W(t) = 40[tex]e^{-0.35t}[/tex]

By the law of indices,

W(t) = 40/[tex]e^{.035t}[/tex]

When t > 0 the value of  [tex]e^{.035t}[/tex] > 1

Thus, t > 0 the value of W(t) < 40

Hence "The value of function W(t) will be less then 40 if t > 0".

For more about the function,

brainly.com/question/23712366

#SPJ2

Which of the following ratios is not equivalent to the other three 2/3 4to6 8to12 4/5

Answers

Answer:

The non-equivalent ratio is 4:5.

Step-by-step explanation:

2/3 4/6 and 8/12 are equivalent because they are all multiples of each other.

If Max wants to build a rectangular walkway 4 ft wide by 1.5 ft deep by 20 ft long
from the house to the storage shed, what is the area of the walkway?
Square Feet

Answers

Answer:

80 ft^2

Step-by-step explanation:

The area of a rectangular walkway = L x W = 20 ft x 4ft =  80 ft

Please answer this correctly without making mistakes

Answers

Answer: take 20% off

Step-by-step explanation:

the first one is correct because you would be getting 20% off of any purchase.

Plz help me with this!?!? I will mark you brainliest plz and thank you!

Answers

Answer:

9

Step-by-step explanation:

Marbles question:

John is told to find 3 specific marbles within a box of 60 marbles. The room is dark and he can’t see the marbles properly. He pours out 20 of these marbles, and blindly chooses 3 of them.


What are the chances he chooses the 3 specific marbles he was told to find?

Answers

The chances he chooses the 3 specific marbles he was told to find is 1/20.

How to calculate the probability?

It should be noted that there are 60 marbles and he wants to find 3.

In this case, he poured out 20. Therefore, his chances of picking the three marbles will be 1 out of 20.

Therefore, the chances will be 1/20.

Learn more about probability on:

brainly.com/question/24756209

#SPJ1

Calculate the constant of proportionality, k, for the given table.

Answers

Answer:

k = y/x

Step-by-step explanation:

1/5, 2/10, 3/15 . . . all equal to 1/5 which is what the value of k is; 'k' stands for constant of proportionality

Question
A globe of Earth is in the shape of a sphere with a radius of 14 inches. Find its a volume and b surface area.
Round the answers to the nearest hundredth.

Answers

Answer:

[tex]Volume = 11488.21[/tex]

[tex]Area = 2461.76[/tex]

Step-by-step explanation:

Given

[tex]Radius, r = 14\ in[/tex]

Shape: Sphere

Solving (a): The Volume

This is calculated as:

[tex]Volume = \frac{4}{3}\pi r^3[/tex]

Take [tex]\pi[/tex] as 3.14 and substitute 14 for r

[tex]Volume = \frac{4}{3} * 3.14 * 14^3[/tex]

[tex]Volume = \frac{4}{3} * 3.14 * 2744[/tex]

[tex]Volume = \frac{4 * 3.14 * 2744}{3}[/tex]

[tex]Volume = \frac{34464.64}{3}[/tex]

[tex]Volume = 11488.21[/tex]

Solving (b): The Surface Area

This is calculated as follows:

[tex]Area = 4\pi r^2[/tex]

Take [tex]\pi[/tex] as 3.14 and substitute 14 for r

[tex]Area = 4 * 3.14 * 14^2[/tex]

[tex]Area = 4 * 3.14 * 196[/tex]

[tex]Area = 2461.76[/tex]

Evaluate 4^2 - 6 ÷ 2 + 3=

Answers

Answer:The correct answer is 16

Step-by-step explanation:

4^2= 16

16-6/2+3

16-3+3

13+3=16

Given the quadratic function f(x) = 4x^2 - 4x + 3, determine all possible solutions for f(x) = 0

Answers

Answer:

The solutions to the quadratic function are:

[tex]x=i\sqrt{\frac{1}{2}}+\frac{1}{2},\:x=-i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

Step-by-step explanation:

Given the function

[tex]f\left(x\right)\:=\:4x^2\:-\:4x\:+\:3[/tex]

Let us determine all possible solutions for f(x) = 0

[tex]0=4x^2-4x+3[/tex]

switch both sides

[tex]4x^2-4x+3=0[/tex]

subtract 3 from both sides

[tex]4x^2-4x+3-3=0-3[/tex]

simplify

[tex]4x^2-4x=-3[/tex]

Divide both sides by 4

[tex]\frac{4x^2-4x}{4}=\frac{-3}{4}[/tex]

[tex]x^2-x=-\frac{3}{4}[/tex]

Add (-1/2)² to both sides

[tex]x^2-x+\left(-\frac{1}{2}\right)^2=-\frac{3}{4}+\left(-\frac{1}{2}\right)^2[/tex]

[tex]x^2-x+\left(-\frac{1}{2}\right)^2=-\frac{1}{2}[/tex]

[tex]\left(x-\frac{1}{2}\right)^2=-\frac{1}{2}[/tex]

[tex]\mathrm{For\:}f^2\left(x\right)=a\mathrm{\:the\:solutions\:are\:}f\left(x\right)=\sqrt{a},\:-\sqrt{a}[/tex]

solving

[tex]x-\frac{1}{2}=\sqrt{-\frac{1}{2}}[/tex]

[tex]x-\frac{1}{2}=\sqrt{-1}\sqrt{\frac{1}{2}}[/tex]                 ∵ [tex]\sqrt{-\frac{1}{2}}=\sqrt{-1}\sqrt{\frac{1}{2}}[/tex]

as

[tex]\sqrt{-1}=i[/tex]

so

[tex]x-\frac{1}{2}=i\sqrt{\frac{1}{2}}[/tex]

Add 1/2 to both sides

[tex]x-\frac{1}{2}+\frac{1}{2}=i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

[tex]x=i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

also solving

[tex]x-\frac{1}{2}=-\sqrt{-\frac{1}{2}}[/tex]

[tex]x-\frac{1}{2}=-i\sqrt{\frac{1}{2}}[/tex]

Add 1/2 to both sides

[tex]x-\frac{1}{2}+\frac{1}{2}=-i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

[tex]x=-i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

Therefore, the solutions to the quadratic function are:

[tex]x=i\sqrt{\frac{1}{2}}+\frac{1}{2},\:x=-i\sqrt{\frac{1}{2}}+\frac{1}{2}[/tex]

Which of the following equations is equivalent to 4x-2=38
A. 5x=-50
B. X-20=30
C. 5x=50
D. 2x=10

Answers

D I hope this helps.

Which is the lower left quadrant on the coordinate plane? A coordinate plane. Quadrant I Quadrant II Quadrant III Quadrant IV

Answers

Answer:

C

Step-by-step explanation:

If u form a C around the origin point, u will know the order.

Answer:

Quadrant 3

Step-by-step explanation:

The quadrants go from:

1                           2

3                          4

christopher bought a six-pack of soda for 1.50. each can holds 2 fluid ounces. identify the total quantity of each unit in the problem a. cans b. dollars c. cents d. six packs e. ounces f. cases

Answers

The total quantity of each unit in the problem is ounces

What is the volume of a can of soda in ounces?

A can of soda weighs about 2 fluid ounces and in pack of soda, there are 2 cans of soda, which means that total quantity of each unit in the problem can be determined in ounces.

Six packs is not a unitary measure, because each pack has 12 cans , which means that six packs translate into 72 cans(6 packs*12 cans), also, the can itself is made of ounces, hence, measuring the unit of soda in cans is not appropriate where each can is about 2 ounces

Find out more about ounces on:https://brainly.com/question/14929476

#SPJ1

Ceecee and Jose ate at a restaurant.
Ceecee gave a 20% tip on an $85 dinner bill.
Jose gave a 18% tip on a $80 dinner bill.
Who (Ceecee or Jose) gave the larger tip?

Answers

I think it’s Jose because 18% but im not sure

Dreyfus cashed a check for $145. The teller gave him five $20 bills, two $20 bills, and f $1 bills. How many $1 bills did he get?

Answers

Answer:

5 singles

Step-by-step explanation:

5 $20= 100

2 $20= 40

remainder is 5 singles

Answer:

5 $1 bills.

Step-by-step explanation:

The expression to reflect this problem is:

145 = 20(5) + 20(2) + 1x

145 = 100 + 40 + 1x

145 = 140 + 1x

145 - 140 = 140 + 1x - 140

5 = 1x

5 ÷ 1 = 1x ÷ 1

5 = x

I hope this helped and if it did I would appreciate it if you marked me Brainliest. Thank you and have a nice day!

At 60 km per hour it takes archie 10 hours to travel from his house in Manila to his house in the province. If his rate will be 120 km per hour, how long will it take him to reach his house in the province from Manila

A. 5 hours
B. 8.5 hours
C. 6 hours
D. 7.5 hours

Pls i need it now

Answers

Answer:

a

Step-by-step explanation:

5 hours

A penguin walks 10 feet in 6 seconds. How far does the penguin walk in 45 seconds

Answers

Answer:

70 ish

Step-by-step explanation:

Other Questions
you create a hash link by assigning unique names to elements in your web page using the html attribute. Jennifer has a total of 25marbles. She gives 5 marblesto her friend, Elizabeth.What fraction of marbles didElizabeth receive? Solve 6^x + 2 = 10 for x using the change of base formula log, y = log y log b How can the strength of a force affect velocity? Now i know that each of the 3 main layers of earth has its own features,as follows. which ratio has the unit rate of 4 Blissful breeze manufactures and sells ceiling fans. Each fan has a unit product cost of $112 and a unit selling price of $190. If blissful breeze produces 900 fans and sells 842 fans this month, the total cost of goods sold will be $______. To which groups of animals are vertebrates most closely related phylogenetically How does this business attract customers and keep them happy? Customer service Creativity and innovation a. It is linear because it has a constant rate of change.b. It is linear because it does not have a constant rate of change.c. It is not linear because it has a constant rate of change.d. It is not linear because it does not have a constant rate of change. Graph the line that represents the equation y= - 2/3 x + 1I will give out brainlist help [please] Paulette is paid 2 1/2 % commission on all sales, and an extra 1 1/2 % on all sales over $6,500. Her sales last week totaled $17,400. What were her total earnings for the week? To collect data on the signal strengths in a neighborhood, Tracy must drive from house to house and take readings. She has a graduate student, Dave, to assist her. Tracy figures it would take her 8 hours to complete the task working alone, and that it would take Dave 12 hours if he completed the task by himself.How long will it take Tracy and Dave to complete the task together? in a random sample of 7 residents of the state of california, the mean waste recycled per person per day was 1.7 pounds with a standard deviation of 0.36 pounds. determine the 99% confidence interval for the mean waste recycled per person per day for the population of california. assume the population is approximately normal. step 1 of 2 : find the critical value that should be used in constructing the confidence interval. round your answer to three decimal places. in a study in industrial/organizational psychology, a sample of office workers use a smartphone app to report their thoughts, feelings, and behaviors with respect to their jobs and coworkers as they go about their workweek. based on this information, the study is most likely as example of: please choose the correct answer from the following choices, and then select the submit answer button. answer choices naturalistic observation. an experiment. a survey. a case study. What effect did reading the Declaration of Sentiments have on you? What were your thoughts and feelings as you read or listened to the speech? Explain what caused your response, using specific examples from the text. if a homozygous tall plant (aa) is crossed with a homozygous small plant (aa), knowing that tall plants are dominant over small plants. what are the resulting genotypes and phenotypes for the f1 and the f2? Do you think smartphones will be useful in 5 years?Will smartphones still be useful or do you think something else will replace them? Why?How will smartphones be useful in 5 years? Factors in the environment that an organisms reacts to, such as light, temperature, sound are known as. Which of the following numbers is rational?A. 25B. 25C. 2piD. 25pi